Preserving the past
Since opening, the museum has experienced multiple instances of weather damage, leading to damaged stone and the need for redecoration. With an authentic building design that places the museum at the heart of Stranraer’s history, a large aspect of this project was completing repairs of the intricate stoneworks featured throughout the building.
Strong emphasis was placed on removing historically applied renders that weren’t in keeping with the building’s listed nature – these had caused unforeseen damage to the building fabric below, so removal was our recommended solution.
Preparing for the future
Various issues were discovered upon commencing on site, including substantial rot damage to roof structures and repairs required to the north block tower spire. This required coordination between the main contractor, rot specialist, design team and client, as well as significant renewals to the sarking, slating and lead renewal.
As the most visible element of the exterior envelope, the tower spire required repairs including an all-new lead roof, full refurbishment of the weathervane and works to circulation ventilation louvres below eaves level.